IVD Expansion Progress Reports |
|
|
|
Capital
Building Projects Home Page
|
You may submit questions or provide feedback regarding this project to Sam Ball.
9/30/08 Progress Report The addition to IVD is on schedule for substantial completion by mid December. It will then take 60-75 days to install IT/Telecom equipment and furniture, and move in staff by the end of March 2009 1/31/08 Progress Report Design of addition to the International Programs office building is nearly complete and permit applications are underway. Construction of this 5,000 square foot addition will provided additional offices, conference rooms and support space for the rapidly growing International Programs. Timeline Construction will commence in May 2008. Occupancy is scheduled for late winter 2009.
|
|