Science Center

 

Capital Building Projects Home Page

Science Center

Project Description

Progress Reports

Project Images

Web Cam

Frequently Asked Questions and Answers

1)

Why construct a new Science Center?

2)

Who is represented on the pre-design team?

3)

What is the timeline and scope of this project?

4)

How was the site selected?

5)

Will environmental concerns be addressed?

6)

Will I have the opportunity for input?

7)   Who is represented on the design team?

1. Why construct a new Science Center?
The existing Science and Technology (ST) complex, constructed in 1965, has exceeded life cycle requirements and is no longer able to support the instructional science program needs for the institution. The Occupational Education Building (OEB), constructed in 1969 is of similar vintage as the ST complex and is also in a similar state of disrepair. The lack of adequate science and health science labs and classrooms is further aggravated by the increasing FTE demands from a rapidly expanding community population base. A request for state funds to proceed into a pre-design stage for this project was approved and a Science Pre-design Team comprised of GRCC instructors, administrative staff, and facilities personnel along with a consultant team from S. M. Stemper Architects began intensive efforts to determine the scope, program, and budget for a new Science Center.

A new facility will allow the college to accommodate increasing enrollment pressure and provide accredited science and health science programs needed to keep GRCC current with industry and marketplace demand. Given the poor condition of the existing facilities, there will be definite operational cost savings with the construction of a new facility that meets current energy standards and is equipped with new energy efficient mechanical and electrical systems. The new facility will afford the opportunity to centralize the college’s ‘wet lab’ science programs, to include chemistry, physics, astronomy, life sciences, geology, and health sciences within one facility.

The proposed new facility is not only identified in the College's 10-year plan and is included in the current master plan, but it is also a key element in the College's master facilities plan. The Pre-design Study will outline the need for this facility and set parameters for its program design, budget, and schedule.

Top of page

2. Who is represented on the pre-design team?
Green River Community College instructors, administrative and facilities personnel along with a consultant team from S. M. Stemper Architects made up the Pre-design Team.

Top of page

3. What is the timeline and scope of this project?
For an up-to-date timeline and scope for this project, please refer to the most recent Science Center Progress Report.

Top of page

4. How was the site selected?
A major institutional master planning decision was made in the proposed siting of both the new Technology Center and Science Center on the athletic field situated between the existing ST and SMT buildings. The utility infrastructure is directly available at the site and concurrent site development for both facilities offers a number of cost and development advantages. Additionally, the programs that are planned in these facilities are well situated for related studies and faculty/staff support in the adjacent SMT building. Another advantage to this location includes the reutilization of existing developed acreage, supporting the College's goal of preserving the natural campus environment and incorporating achievable elements of sustainable design.

The major disadvantage of utilizing this site for the new Technology Center and a future Science Center is the loss of the athletic field. Replacing the track function and playing field will be aggressively addressed in the developing master plan through future campus design options.

Top of page

5. Will environmental concerns be addressed?
GRCC is blessed with a beautiful natural setting and a statement will be made in sustainable design along with the assumed energy conservation features it should achieve. A key component for the pre-design study will be defining sustainable design concepts that are appropriate for this project. This effort will include exploring the possibilities for natural day lighting, native landscaping, natural ventilation, and energy efficient mechanical systems. An energy efficiency life cycle cost analysis will be provided to ensure that long range cost benefits are considered.

Top of page

6. Will I have the opportunity for input?
You may submit your questions regarding this project by sending an e-mail to Sam Ball.

Our project team will review questions asked and submit replies to the inquirer.

In an effort to keep you informed as to the plans and progress of the project, this website will be periodically updated.

7. Who is represented on the design team?
Green River Community College instructors, administrative and facilities personnel along with a consultant team from S. M. Stemper Architects make up the Design Team.

Top of Page

Last updated on: 04/03/2006
Copyright© 2009 Green River Community College. All rights reserved.
Page Footer Contact