Technology Center

 

Capital Building Projects Home Page

Technology Center

Project Description

FAQ's

Project Images

 

You may submit questions or provide feedback regarding this project to Sam Ball

This Web site will be periodically updated
.

5/19/05 Progress Report   

After several months of delay, all regulatory inspections are in the finals stages of completion. During the delay, we were allowed to install furnishings and equipment in preparation for staff and faculty to move into the building.  On May 16th, the Information Technology Client Services Team began their move into the new facility. Faculty moves will begin soon.      

The boiler replacement is still scheduled to occur during the summer months and will not delay public access to the building or the use of the building during summer quarter. 

View Capital Projects Status Report for an up-to-date timeline.

3/17/05 Progress Report 

Unfortunately, a subcontractor failed to deliver and install their product as scheduled, resulting in a delay of required fire systems testing. Public use of the building therefore is delayed until late April/early May.  This will prevent scheduling spring quarter classes in the new facility. 

Graham construction, our general contractor, has allowed us to install furnishings and equipment in designated rooms and that effort will continue as planned.  Other rooms will be set up as secure storage areas until the unfinished rooms are completed.     

Also, we have a problem with the boilers in the center.  As a result, the contractor will replace the boilers after the heating season.  This replacement effort will not delay public access to the building.

View Project Status Report

Timeline 

Program Move-in: Winter-Spring Quarters 2005

Occupancy: May 2005

12/27/04 Progress Report 

The Technology Center is in the final stages of construction. Over the last several weeks, the required testing of mechanical, electrical, fire, plumbing, and other infrastructure systems has been ongoing.  As well, interior finishes are nearly complete. 

The Technology Center Design Team continues to be consulted during this final stage of construction. 

The project will be substantially complete by the end of January, 2005 

Timeline
Occupancy: January  2005
Program Move-in: Winter-Spring Quarters 2005



5/19/04 Progress Report

Construction is proceeding on schedule with final grading and asphalting a priority effort to take advantage of dry weather. Glass installation is continuing and will be completed by the end of the month. Installation of roofing and exterior metal is underway.

The project is still on track to be completed by the end of December 2004.

Timeline
Occupancy January 1, 2005
Program Move-in Winter-Spring Quarters 2005
 

1/21/04 Progress Report

Construction is proceeding on schedule with concrete foundations and floor slabs substantially complete. Erectors will begin installing structural steel later this month and the building will begin to take shape. The project is still on track to be completed by December 2004.

Timeline

Item Completion
Construction Start 08/01/03
50% Complete 03/15/04
Substantial Completion 11/01/04

10/15/03 Progress Report 

Construction of a two-story 31,000 square foot Technology Center on the east portion of Green River’s track and field has begun. 

Graham Contracting Ltd., a division of the Graham Group of Companies was selected as the general contractor. The Graham Group provides construction services in the Pacific Northwest and Western Canada. Their stated commitment is to supply high quality, competitive services in meeting clients' needs. 

S. M. Stemper Architects has provided a new rendering of the building. 

The Technology Center Design Team will be consulted throughout the construction period. 

Timeline  

Item                                         Completion

Construction began                   October, 2003
Occupancy                              January 1, 2005

07/15/03 Progress Report

The state has approved $10,984,800 for the construction of the new two-story, 31,000 square foot Technology Center.

Permit plans were submitted to King County in January and the final stages of the approval process will soon be completed.  The plans were submitted for construction bids in June, with bids due on July 17, 2003.

Construction is scheduled to begin in August 2003 with completion in January 2005.

Members of the Technology Center Design Team will continue to be consulted throughout the construction period.

03/14/03 Progress Report

Permit plans were submitted to King County on January 16, 2003. The architectural team is completing the final plans an specifications that will be used in the general contractor bidding process.

Several members of the Technology Center Design Team are currently focusing on security systems and the selection and configuration of classroom furniture for the new center.

The Technology Center will be a two-story structure containing approximately 31,000 square feet and is estimated to cost $10,000,000.

With funding approval from the state during the spring 2003 legislative session, and the building permit process completed, construction should begin in July of 2003 with completion in December 2004.

09/12/02 Progress Report

During the summer break, the architects, using input from the relevant programs, are creating bid documents and specifications. During fall quarter, faculty will need to participate in determining the best use of existing space that will be freed up as a result of the new Technology Center.

The Technology Center concept involves a two-story structure containing approximately 31,000 square feet and is estimated to cost of $10,000,000.

With continued funding approval from the state, and the building permit process completed, construction is slated to start in July 2003 with completion in December 2004.

 

Last updated on: 04/03/2006
Copyright© 2009 Green River Community College. All rights reserved.
Page Footer Contact